Pulsar Helium
Pulsar Helium: Topaz Development Valuation
A current preliminary project DCF linking resource conversion, sustained well deliverability, processing capacity, installed cost, financing, dilution, CO₂ economics, and market-implied expectations.
Thesis
A source-backed valuation of Pulsar Helium's Topaz project that distinguishes contingent and prospective resources from reserves, short-duration test rates from sustainable commercial feed, the reserved equipment package from all-in installed cost, and project funding from common-shareholder value.
Open the integrated Topaz valuation model.
Key chart
| Scenario | Estimated value per share | Weight | Interpretation |
|---|---|---|---|
| Constrained development and financing stress | C$0.10 | 25% | Low sustained feed, negative project DCF, and heavily discounted equity funding |
| Sustained-feed-constrained Base development | C$0.19 | 50% | Eight well equivalents, approximately 60% field-supported utilization, and material residual equity funding |
| High-deliverability and option-value case | C$1.76 | 25% | Strong well productivity, 85% utilization, better pricing and financing, plus early-stage option value |
The argument
Topaz can become a strategically valuable primary-helium project, but the value chain contains several separate gates:
- convert contingent and prospective resources into commercially recoverable reserves;
- prove sustained multi-well deliverability rather than short-duration peak flow;
- execute a definitive processing and liquefaction purchase agreement;
- complete the plant, gathering, power, storage, loading, CO₂, and site infrastructure;
- secure bankable helium and CO₂ offtake terms;
- finance the development without transferring or diluting most of the project economics; and
- commission and operate the system at adequate uptime and recovery.
The model gives each gate explicit treatment. It does not award full nameplate economics merely because a processing package has been reserved, and it does not treat prospective resources as proved inventory.
Model AssumptionThe model uses 228.810 million current fully diluted shares before future project-financing dilution and a C$1.42 reference market price as of the valuation date.What changed from the prior valuation
The earlier framework identified the resource-versus-nameplate mismatch, but it still allowed the strategic operating case to assume utilization that was not directly constrained by sustained field deliverability. The refined model adds five major controls.
Sustained well feed constrains utilization
The 940-litre-per-hour package is a processing ceiling, not a production forecast. The model calculates the raw-gas feed required to support output using helium concentration, processing recovery, uptime, and modeled sustained flow per well.
The Base case uses eight producing-well equivalents at 0.75 MMcf/day each. That supports approximately 60% of plant nameplate, below the 70% commercial-utilization target. Approximately 9.3 comparable well equivalents would be needed to support 70% utilization under the Base composition and recovery assumptions.
FactCompany technical disclosures reported short-duration natural-flow observations and a higher compressor-assisted peak at Jetstream #1. The model does not treat the compressed peak as a demonstrated multi-year production plateau.Jetstream #2 is separately risked because the well was mechanically restricted and required remediation. The Base case does not automatically treat it as a fully productive development well.
Resource classification remains intact
The competent-person report contains contingent and prospective resources, not reserves. The model therefore applies separate assumptions for geological success, resource expansion, recovery, and development probability.
The Base case produces approximately 164.9 MMcf of modeled risked recoverable helium. That figure is an analytical bridge, not a company reserve estimate. It covers only a fraction of the gas required by a long-lived development case, so the central valuation still depends on successful appraisal, conversion, and expansion.
Installed cost extends beyond the equipment package
The approximately US$78.7 million indicative package price does not represent a complete commissioned project. The Base sources-and-uses schedule also includes:
- development wells and remediation;
- gathering and field infrastructure;
- power and electrical systems;
- civil and site work;
- storage and tanker loading;
- CO₂ handling;
- engineering and owner costs;
- commissioning and working capital; and
- contingency.
The Base case estimates approximately US$122 million of all-in installed plant cost and roughly US$146 million of total remaining pre-production uses. Confidence remains low until definitive equipment, engineering, construction, and infrastructure scopes are disclosed.
Financing is carried through to common shares
The model begins with the July 2026 financing and the company-reported fully diluted security count. It then estimates project debt, strategic-partner capital, remaining liquidity, and the residual equity requirement.
The Base case assumes US$55 million of project debt and a strategic partner funding 10% of the plant. The partner is also assigned a corresponding 10% economic share; its capital is not treated as free money.
After those sources, the Base case still has an estimated US$51 million equity gap. At the modeled financing price, this creates approximately 64 million new shares, taking the illustrative fully funded denominator to roughly 293 million shares.
That dilution is a central reason the Base fully funded value is materially below a calculation that divides gross project value by only today's share count.
Helium pricing and netback
The model uses a project netback rather than applying a headline retail liquid-helium price directly to production. The netback must absorb or reflect purification, liquefaction, storage, handling, transportation, distributor economics, product specifications, customer terms, and any discounts embedded in financing or offtake agreements.
The Base case starts at US$22 per liquid litre, equivalent to roughly US$550 per Mcf before escalation. This is an analyst assumption, not a disclosed Pulsar contract price.
The current enterprise value is demanding under the Base risk weight. The price bridge indicates that, holding other Base assumptions broadly constant, a substantially higher starting netback would be needed to support the market value without assigning additional resource, plant-option, or corporate optionality.
CO₂ economics
The reserved package includes approximately 300 tonnes per day, or about 109,500 tonnes per year, of nameplate CO₂ capacity. The model scales actual CO₂ output to gas feed and plant utilization rather than assuming full nameplate production independently of helium operations.
At the Base US$40-per-tonne netback, CO₂ provides a useful operating contribution but remains a small portion of modeled peak revenue. Commercial value will depend on purity, local demand, storage, loading, transportation distance, customer qualification, and actual offtake pricing.
Scenario analysis
Constrained case — C$0.10 per fully funded share
The constrained case assumes four well equivalents at 0.30 MMcf/day, approximately 9.5% field-supported utilization, a US$12-per-litre starting helium netback, higher installed cost, and a 22% discount rate.
The project DCF remains negative, so no operating-project value is recognized. Equity value is principally the modeled net-liquidity balance spread across a substantially larger fully funded share count.
Base case — C$0.19 per fully funded share
The Base case assumes eight well equivalents at 0.75 MMcf/day, approximately 60% field-supported utilization, a US$22-per-litre starting netback, a 15% discount rate, US$122 million of installed plant cost, and material equity financing.
The un-risked development NPV is positive but modest relative to the current market enterprise value. After development probability, partner economics, financing needs, and dilution, the fully funded common-share value is approximately C$0.19.
Upside case — C$1.76 per fully funded share
The upside case assumes ten well equivalents at 1.30 MMcf/day, 85% utilization, a US$28-per-litre starting netback, lower installed cost, stronger debt availability, and US$40 million of Falcon, corporate, and helium-3 option value.
This is intentionally demanding. The 1.30 MMcf/day input was a compressor-assisted test peak, not a proved multi-year sustained rate. The case also requires further resource conversion and assigns value to options that may never become commercial.
Market-implied expectations
The model does not conclude that the market is necessarily wrong. It identifies what the market must be assuming that the Base case does not yet prove.
Potential explanations include:
- a much larger connected resource than the currently risked inventory;
- sustained rates nearer the compressor-assisted test result;
- faster and more successful development drilling;
- premium liquid-helium offtake economics;
- lower equipment, EPC, infrastructure, or contingency costs;
- more project debt and less equity dilution;
- valuable third-party gas processing;
- commercial helium-3 recovery; or
- strategic acquisition value not captured by a stand-alone DCF.
The market can be correct only if enough of these favorable assumptions become evidenced and economically retained by Pulsar shareholders.
Catalysts
Evidence that would justify raising completion probabilities or reducing required returns includes:
- a definitive plant purchase agreement with complete scope, price, milestones, warranties, and financing;
- successful Jetstream #2 remediation;
- sustained multi-day or multi-week flow testing with pressure and decline data;
- repeatable well performance across the six-well program;
- an updated independent resource estimate with meaningful conversion to reserves;
- bankable helium and CO₂ offtake agreements;
- committed project debt with disclosed covenants and equity requirements;
- final engineering, permitting, construction, and commissioning milestones; and
- demonstrated helium recovery, product purity, uptime, and operating cost.
Risks and disconfirming evidence
The valuation should be reduced if new wells fail to reproduce the expected helium concentration or flow, commercial decline is steeper than modeled, the connected reservoir is smaller or more compartmentalized, plant and EPC costs exceed contingency, the equipment transaction or delivery slips, offtake terms transfer value away from Pulsar, debt availability is lower, CO₂ cannot be sold economically, or helium-3 separation is uneconomic.
Detailed conclusion
Pulsar has a credible path to an unusual primary-helium development, but the project remains between discovery and bankable commercial execution. The most important variable is not the theoretical output of the liquefaction package. It is the amount of sustained, recoverable, financeable helium feed that can reach that package over time.
Under the current evidence set, the Base case does not support the market reference price. The upside case can, but only by assuming much stronger deliverability, resource conversion, pricing, financing, and option value than has been demonstrated.
The appropriate way to use the model is as an evidence-updating system. Each drilling result, flow test, resource report, plant contract, offtake agreement, financing term, and construction milestone should change specific assumptions rather than merely reinforce a narrative.
Audit this conclusion
The conclusion can be summarized elsewhere. The full Ephesus Research page remains the place to inspect the calculation, evidence, sensitivities, revisions, and contrary evidence behind it.
Evidence guide
Evidence and judgment labels
Statements marked Fact are intended to be directly supported by cited evidence. Guidance, estimates, assumptions, inferences, and speculation remain separately named so they are not mistaken for verified facts.
13
mapped sources
Yes
primary support
Evidence map
Mapped public sources
Version control
Article change log
Research status
Research status
Current
Conclusion
Mixed
Version
1.0.0-preliminary
Last reviewed
Aug 5, 2026
Access
Public and free
Continue reading
Related public research
Ucore Rare Metals
Ucore Five-Year Corporate SOTP: Louisiana Is the Core, but It Is Not the Whole Portfolio
The Louisiana SMC is Ucore's principal operating asset, but it is not the entire portfolio. This five-year SOTP separately values Louisiana, a risked Canadian Sm/Gd SMC, Bokan-Dotson Ridge, external RapidSX optionality, corporate cash and overhead, then models the funding and dilution required to reach commercial scale.
IREN
IREN: Five-Year DCF and Buildout Valuation
A current preliminary cohort-cash DCF mapped to the live Google Drive workbook. The analysis distinguishes IREN's official capacity stages, cohort financing, five-year primary GPU life, non-core post-contract tail economics, residual support, revenue sharing, and public community-model reference outputs.
SPCX
SpaceX AI: Probability-Weighted Sum-of-the-Parts Valuation
A current probability-weighted sum-of-the-parts DCF based on SpaceX's filed segment results, disclosed AI contracts, buildout targets, capital requirements, dilution, institutional market checks, and an explicitly low-probability Elon Case.
Challenge a fact, formula, or interpretation.
Submissions are reviewed before publication. Credited contributors are listed only with permission; private email addresses are never displayed publicly.